Good afternoon! I wish I would have found this great forum before I started the construction process, but am glad to have found it nonetheless.
We started the bid process back in early March, and selected our PB (and signed a contract) on April 2nd. After some permitting and weather delays, dig day was 5/11.
Plumbing went in 5/14 and rebar was done on 5/15. Shotcrete was delayed until 5/21 and the waterline tile went in 5/25. Currently waiting on stone and rock to be delivered tomorrow and hopefully install on Thursday although with all the rain we have had, I am not so sure!







We started the bid process back in early March, and selected our PB (and signed a contract) on April 2nd. After some permitting and weather delays, dig day was 5/11.
Plumbing went in 5/14 and rebar was done on 5/15. Shotcrete was delayed until 5/21 and the waterline tile went in 5/25. Currently waiting on stone and rock to be delivered tomorrow and hopefully install on Thursday although with all the rain we have had, I am not so sure!






