After nearly 3 months from signing our contract, we finally had our dig on June 5th! The delay was just due to a little bit of rain that we had here in Texas.
The steel and plumbing are done, we passed our first inspection, and we're hoping for gunite by the end of the week. We were going to get Emerald Bay from the Crystal Stones Designer Series, but I think we're going to switch to Gray Harbor in the Crystal Stones Smooth collection. This decision may drive me crazy before it's over. Also, you'll see in my signature that we're having an in-line chlorinator w/ozone & uv installed. Just wanted to let you know that I did try to talk hubby out of that, to no avail. so hoping for the best. Here are some pictures for you, as I know you love pictures! Let me know what you think! 