Hi everyone! I am a new pool owner (16'x48" metal frame) and this is my first post.
I live in East TN. We have a sloped yard and we paid someone to level the ground and put up our pool. We expressed concerns about it clearly not being level before the pool went up but we were assured it was level because a very expensive transit was used. Underneath the pool is bumpy which doesn't bother us so much, but the pool itself looks awful and possibly unsafe even though the waterline appears to only be about 1-1.5" off at the worst spots. It isn't all leaning to one side or anything like that, however. If you were to draw an x over the pool, both ends of one diagonal line of the x are high and both ends of the other are low (almost exactly the same amount). The center is fairly level except for the bumpiness we believe.
What options do we have when we take the pool down so it has a more level base for next year? I know the correct answer is to dig to match the lowest points, but since part of the issue is that he dug too deep on the high side of the slope, if we do that at this point the entire pool site will be at least 2-3" lower than the lowest side of the slope, essentially placing the whole pool in a big hole.
Given the circumstances, what would be the easiest and least expensive option for leveling it out at this point without potentially causing some other issue down the road? Could some of the clay dirt be put back down and compacted if left alone to compact further all fall/winter/spring, or would it potentially still not be stable enough by then? Or could a thin layer of cement or some kind of soil/sand/cement mix be spread on top to fill in the low spots? Any ideas/thoughts would be greatly appreciated! I wouldn't be opposed to just having a concrete slab poured, but cost is a huge factor as we've already spent a ton of money on this $270 pool so it has already gotten quite out of hand lol. Also, anything that would require digging any deeper than the existing lowest point is out because he already hit and removed some of the rocks surrounding the septic tank drain field.
I have attached an image for reference, but it does look a bit worse now so I will take some new images tomorrow. Thank you!
Heather
I live in East TN. We have a sloped yard and we paid someone to level the ground and put up our pool. We expressed concerns about it clearly not being level before the pool went up but we were assured it was level because a very expensive transit was used. Underneath the pool is bumpy which doesn't bother us so much, but the pool itself looks awful and possibly unsafe even though the waterline appears to only be about 1-1.5" off at the worst spots. It isn't all leaning to one side or anything like that, however. If you were to draw an x over the pool, both ends of one diagonal line of the x are high and both ends of the other are low (almost exactly the same amount). The center is fairly level except for the bumpiness we believe.
What options do we have when we take the pool down so it has a more level base for next year? I know the correct answer is to dig to match the lowest points, but since part of the issue is that he dug too deep on the high side of the slope, if we do that at this point the entire pool site will be at least 2-3" lower than the lowest side of the slope, essentially placing the whole pool in a big hole.
Given the circumstances, what would be the easiest and least expensive option for leveling it out at this point without potentially causing some other issue down the road? Could some of the clay dirt be put back down and compacted if left alone to compact further all fall/winter/spring, or would it potentially still not be stable enough by then? Or could a thin layer of cement or some kind of soil/sand/cement mix be spread on top to fill in the low spots? Any ideas/thoughts would be greatly appreciated! I wouldn't be opposed to just having a concrete slab poured, but cost is a huge factor as we've already spent a ton of money on this $270 pool so it has already gotten quite out of hand lol. Also, anything that would require digging any deeper than the existing lowest point is out because he already hit and removed some of the rocks surrounding the septic tank drain field.
I have attached an image for reference, but it does look a bit worse now so I will take some new images tomorrow. Thank you!