**updated with equipment list for critique**

We are building a pool in Dallas, TX. Our builder just completed a remodel on my parents pool (was supposed to be a 4 week project and turned into 3 month project) he is now started my pool (a full 2 months after it was supposed to be completed, due to delays with gunite and covid).
Initially we had couldn't get a neighbor to take down a fence (so we would only have a 4 ft, access, which he charged us a $2000 premium to dig the pool, and eventually a neighbor agreed to remove their fence to help us out, but he now claims he is still using the small equipment so the charge will remain)
We had him start on Feb 2 and it took 2 days to dig the pool, after which he stated the county will do an inspection and then he can continue with steel and plumbing (I didn't see anyone from the county on our cameras, but he says they approved us to move forward) it has been 5 days an no subs have come since, he now says the ground is too cold to do plumbing, etc.
We are worried that this may be his method of working and may be in for a very long and drawn out pool build process.
Can someone help understand what is acceptable for build time?
For reference we are building a
32 x 16 pool with a 9 x 9 hot tub
600 ft of concrete
Thanks in advance and looking forward to learning from the group.

We are building a pool in Dallas, TX. Our builder just completed a remodel on my parents pool (was supposed to be a 4 week project and turned into 3 month project) he is now started my pool (a full 2 months after it was supposed to be completed, due to delays with gunite and covid).
Initially we had couldn't get a neighbor to take down a fence (so we would only have a 4 ft, access, which he charged us a $2000 premium to dig the pool, and eventually a neighbor agreed to remove their fence to help us out, but he now claims he is still using the small equipment so the charge will remain)
We had him start on Feb 2 and it took 2 days to dig the pool, after which he stated the county will do an inspection and then he can continue with steel and plumbing (I didn't see anyone from the county on our cameras, but he says they approved us to move forward) it has been 5 days an no subs have come since, he now says the ground is too cold to do plumbing, etc.
We are worried that this may be his method of working and may be in for a very long and drawn out pool build process.
Can someone help understand what is acceptable for build time?
For reference we are building a
32 x 16 pool with a 9 x 9 hot tub
600 ft of concrete
Thanks in advance and looking forward to learning from the group.
Last edited: